Lincoln High School New Classroom Block

Lincoln High School New Classroom Block

Lincoln has experienced a rapid increase in population post EQ and the addition of 6 new classrooms was required to accommodate this.

Client Ministry of Education

Dates September 2016 - May 2017

More Info

Task
Construction of a classroom block, working in an operational school environment, so maintaining minimal disruption to the school and its extra-curricular activities.

Solution
Our programme of work was created to allow for exam break periods and maximise out-of-school hours.

With a combination of precast panels and structural steel, our teams installed the precast panels in the reverse way to ensure an architectural finish on the interior of the project.

Through daily communication with the school, we are ensuring that the school staff is happy with the works and feel fully informed. We are currently on track to finish this project on time with an excellent finish.

Key Project Facts
Total Project Value $1.7 million.
Programme allows for site to be shut down during key exam times.
Outstanding architectural interior finishes through pre-cast panel erection.
Programme tracking on time.